Point To Remember For Civil Construction Site

Following are the few general point to remember at civil construction site to make the construction work easy while maintaining quality of construction.

  • Lapping is not allowed for the bar having diameters more then 36mm.
  • For dowel rod minimum of 12mm diameter should be used.
  • Chair specing maximum is 1000mm.
  • Longitudional reinforcement not less than 0.8% and more than 6% of gross C/S.
  • Chair minimum of 12mm dia meter bar to be used.
  • Mainb bar in the slab shall not be less than 8mm to 10mm and distributor not less than 8mm and not more than 1/8 of slab thickness.
  • Minimum bar of square column is 4nos and 6nos for circular column.
  • Diamension tolerance for cube is +2mm.
  • Minimum thickness of slab is 125mm.
  • Free fall concrete is allowed maximum to 1.50m.
  • Lap slice not be used for bar larger than 36mm.
  • Water absoption of brick should not be more than 15%.
  • Compressive strength of bricks is 3.5N/sqmm.
    • PH value of water should not beless than 6.
      • In soiol filling as per IS Code, 3 sample should be taken for core cutting test for every 100sqm.
      • In steel reinforcement binding wire required is 8kg per MT.

      Density of material

                          Material                                                                          Density

                           Bricks                                                                         1600-1920 kg/cubicmeter
                           Concrete Block                                                          1920 kg/cubicmeter
                           Reinforced Concrete                                                   2310 kg/cubicmeter

      .
      Curing time for RCC members for different type of cement

      Super Sulphate Cement -- 7 Days.

      Ordinary Portland Cement -- 10 Days.

      Mineral and Admixture Added Cement -- 14 Days.


      De-Shuttering Time of Difference RCC Member

      Fore Columns, Walls, Verticle Formworks:-- 1Day.

      Soffit Formworks to Slabs :-- 3Days.

      Soffit to Beam Props :-- 7 Days.

      Beam spanning over 4.5m :-- 14 Days.

      Beam spanning upto 4.5m :-- 14 Days.

      Arches spanning over 6m :-- 21 Days.

      Arches spenning upto 6m :-- 14Days.

      Concrete Sample Required for Different Quantity of Concrete


      Quantity of concrete                                                             No of cube required

      1-5 cum                                                                                          1No
      6-15 cum                                                                                        2Nos
      16-30 cum                                                                                      3Nos
      31-50 cum                                                                                      4Nos
      Above 50cum                                                                       4+1 Nos of addition of each 50cum

          

                                             